Wire rope replacement service
The installation and replacement of wire ropes are operations with strong technical requirements and safety requirements. Once the wire ropes of some structures are not scientifically installed, the service life of the wire ropes will be seriously affected or even scrapped on the spot. Golink has built a strong technical equipment service team and has locations in major ports across the country. In addition to providing maintenance services for port terminal equipment, the steel rope replacement business is also the main service project.
Ordering Consultation
Service Hotline:
|
Product Introduction
起重机钢丝绳换绳服务:
1、主提升绳换绳2、辅助提升绳换绳
3、小车牵引绳换绳
4、变幅绳换绳
钢丝绳换绳要求:
钢丝绳不能用使用时间来衡量,应该用使用频率来检查是否更换。钢丝绳钢丝一定要保证抗拉强度、硬度、延伸率达标,如果钢丝绳的钢丝不达标有可能一用就断丝。
使用要检查, 钢丝绳的磨损、锈蚀、拉伸、弯曲、变形、疲劳、断丝、钢丝绳绳芯露出的程度。 每使用4个月涂油一次,使用时注意负荷指标,在高温物件上使用的钢丝绳,必须采取隔热措施,以防降低强度和寿命。
钢丝绳内的断丝数达该绳总丝数的10%、钢丝绳表面层钢丝腐蚀或磨损达表面原丝径的40%、钢丝绳直径减少量达7%等应该选择更换了。
案例:卸船机钢丝绳换绳
一、更换前我们需要做好施工现场的准备
施工场地应有足够面积,无妨碍作业的障碍物,人员车辆出入通道明确,视线开阔。卸船机下好大车锚定,大梁处于水平位置,小车在后方检修位置锚定。 确认钢丝绳型号通常为6*36sw+iwrc或者8*36sw+iwrc、捻向后将新钢丝绳卷用托架稳妥架好,位于小车正下方投影点5米-10米距离。
二、施工程序
抓斗闭斗下放至码头面时(零位),拆除起升/开闭凸轮限位,做好记号,同时旁路PLC下降限位。
抓斗开斗放置于码头面,解除钢丝绳与抓斗连接。
将钢丝绳端放至码头面,记录下卷筒上钢丝绳剩余圈数。
拆除小车横行轴系中万向联轴节,做好记号。(如四绳同时更换则不必此步骤)
由机房内操作待更换钢丝绳下降,最终在卷筒上保留2-3圈。
用麻绳固定钢丝绳后,拆除卷筒上钢丝绳压板。
用辅助绳与待更换钢丝绳插套做对接头,待更换钢丝绳绳端焊接M30螺母1只,辅助绳与待更换钢丝绳插套不少于6个捻距,连接好后解除固定的麻绳。
如只需更换1根钢丝绳,此时必须将不更换的钢丝绳所在卷筒轮边制动器锁止(关闭节流阀),同时手动打开小车横行制动器。如双绳同时更换则不必此步骤。
由机房操作将待更换钢丝绳全部放至码头面,解除辅助绳与待更换钢丝绳接头。
用辅助绳与新钢丝绳插套做对接头。要求与步骤7同。
由机房操作将新钢丝绳拉上至卷筒上。
固定卷筒钢丝绳压板,压板螺母紧固力矩为1960NM(使用力矩扳手)。
继续起升钢丝绳至卷筒上达到步骤3中记录下的圈数。
在码头面切断新钢丝绳,做头,保持四钢丝绳自由悬垂时长度与旧绳一致。
连接小车横行轴系中万向联轴节。
恢复轮边制动器、小车横行制动器、起升/开闭凸轮限位、PLC下降限位至工作状态。
连接好抓斗,完成。
三、卸船机钢丝绳牵引中注意事项
卸船机小车正下方人员车辆不得进入。地面与机房均应指定专人发令,通过对讲机联系。
对讲机配备:机房负责人1台,地面负责人1台,起升下降操作者1台。 钢丝绳牵引过程中应保持慢速平稳,尤其在接头通过各滑轮时应有专人监护。
地面新钢丝绳卷应安排人员随时卷动将钢丝绳预先放出,不要使新钢丝绳在牵引过程中受到绳卷的阻力。所有人员应位于安全位置,随时注意钢丝绳动态。无关人员不得进入作业现场。